Caltrans PCH & Topanga Cyn Blvd Weekly Closure Schedule for Palisades Fire Repair Work Jan. 25 - Feb. 1
PCH — Temescal Cyn Rd (Pacific Palisades) to Carbon Beach Ter (Malibu)
Current conditions
- Temescal Cyn Rd–Sunset Blvd: 35 mph, cones/signage
- Sunset Blvd–Carbon Beach Ter: Active work zone, single-lane closures, 25 mph
- Possible weekday lane closures 9 AM–3 PM anywhere along PCH
Planned work zones
- Trancas Cyn Rd–Guernsey Ave & Corral Cyn Bridge: Work zones; possible night closures
- S of Las Flores–Sunset Blvd: Fire-damage, drainage & slope repairs; lane closures 9 PM–6 AM weekdays
- S of Big Rock Dr: Catchment wall; NB reduced to 1 lane, 9 AM–3 PM weekdays
- Las Flores–Topanga (SCE trenching):
– NB closed: 4 AM–3 PM weekdays; 4 AM–4 PM weekends; 9 PM–6 AM daily
– SB closed: 9 AM–5 PM weekdays; 4 AM–4 PM weekends; 9 PM–6 AM daily
- S of Topanga Blvd: Slope & culvert work; NB closed 6 AM–3 PM weekdays
- Coastline Dr–Porto Marina Way (Getty Villa): Retaining wall; NB closed 9 AM–3 PM weekdays
Topanga Cyn Blvd — PCH to Grand View Dr
- Closed to the public midnight–5 AM daily
- One-way traffic w/ pilot car (PM 2.5–2.8) for emergency work
- One-way traffic for SCE trenching (PM 4.3–6.7), 8:30 AM–4:30 PM weekdays
Drive cautiously. Fines doubled in work zones.
Expect delays; closures are weather-permitting and subject to change.
View QuickMap for road conditions and closures here.
For Project details, click here
Drive safe, Malibu.