Caltrans PCH & Topanga Cyn Blvd Weekly Closure Schedule for Palisades Fire Repair Work Jan. 12–18
PCH — Temescal Cyn Rd (Pacific Palisades) to Carbon Beach Terrace (Malibu)
Current conditions
• Temescal Cyn Rd–Sunset Blvd: 35 mph, cones/signage
• Sunset Blvd–Carbon Beach Ter: Active work zone, single-lane closures, 25 mph
• Possible weekday lane closures 9 AM–3 PM anywhere along PCH
Planned work zones
• Trancas Cyn Rd–Guernsey Ave & Corral Cyn Bridge: Work zones; possible night closures
• S of Las Flores–Sunset Blvd: Fire-damage repairs; lane closures 9 PM–6 AM daily
• S of Big Rock Dr: Catchment wall; NB 1 lane weekdays, 9 AM–3 PM
• Las Flores–Topanga (SCE trenching):
– NB closed: 4 AM–3 PM weekdays; 4 AM–4 PM weekends; 9 PM–6 AM daily
– SB closed: 9 AM–5 PM weekdays; 4 AM–4 PM weekends; 9 PM–6 AM daily
• S of Topanga Blvd: Slope/culvert work; NB closed 6 AM–3 PM weekdays
• Coastline Dr–Porto Marina Way (Getty Villa): Retaining wall; NB closed 9 AM–3 PM weekdays
Topanga Cyn Blvd (SR-27) — PCH to Grand View Dr
EXTENDED WEEKEND FULL CLOSURE
🗓12:01 AM Sat, Jan. 17 – 7 AM Mon, Jan. 19 (3.6 miles closed)
• Closed to public midnight–5 AM daily
• One-way traffic w/ pilot car (PM 2.5–2.8) 5 AM–midnight
• SCE trenching (PM 4.3–6.7) 8:30 AM–4:30 PM, weekdays
Drive cautiously. Fines doubled in work zones.
Expect delays; schedules may change due to weather/emergency work.