#Malibu Cyn Pole Replacement, Harbor Vista to Piuma, nights 9PM-6AM, days 9AM-3PM through March 2018

Construction on the Southern California Edison (SCE) Malibu Canyon Pole Replacement Project began April 17, 2017 and completion is expected by March 2018. No construction will take place on holidays or during peak summer months of June to October.

The project area includes a 3.5 mile stretch of Malibu Cyn Rd, between Harbor Vista Dr and Piuma Rd. The construction schedule is as follows:

• Day work (Monday-Friday, 9:00 AM-3:00 PM) will be located on the shoulder of Malibu Cyn Rd - no lane closures and minimal traffic impacts
• Night work (Sunday-Thursday nights, 9:00 PM-6:00 AM) will include lane closures and drilling in some areas
• Travelers on Malibu Cyn Rd can expect to see large equipment, including dump trucks, backhoes, and drilling rigs
• Digital traffic signs alerting motorists to the project have been placed at Malibu Cyn Rd and Piuma Rd, and on Malibu Cyn Rd near Malibu Knolls, as per approved LA County traffic control plans

Motorists should expect delays during construction hours, and use alternate routes when possible.

Facebook Twitter Google Plus Email

Latest Update:

June 16, 2017 1:44 PM

The project is on hiatus for the summer months. Construction will resume in October 2017.